Project Updates

Playground:

  • Completed preparation of  forms for the implementation of the DPA program and updated policies and procedures
  • Continued work on the Royal Park RFQ/RFP

Updating plans and preparing 90% submittal.

  • Received BNSF Review.
  • Working towards 60% submittal.

1. Public Engagement Plan

a. The second Stakeholder/Public Meeting was held on August 16th.
b. The third and final Stakeholder/Public Meeting was held December 8th

Coordinating utility construction details, finalizing 90%  grading plans submittal.

Removed & replace curb at Little River Parking lot for ramp installation.

  • Staff continues to assist City of Moore IT with the ArcGIS Server and Portal for ArcGIS.\

For the month of June:

Engineer Update: Project construction began approximately May 1, 2017. Television inspection has been completed for a portion of the line to be rehabilitated.

Still waiting on decision for electrical connection at Whispering Oaks.

Final engineering plans in final review process.

Final review of final landscape design plans and coordination with Meshek. 

The Comprehensive Plan update has been completed.

Plans in final review process.

Geotechnical work is under for footing/pier design of the pedestrian bridge. Geotechnical work has been completed. Bridge pier/footing design has not yet started.

Quantities and notes sheet updating. Quality Assurance and Quality Control review from Principal Engineer. Submitted 60% plans for review.

1. Public Engagement Plan
     a. The second Stakeholder/Public Meeting was held on August 16th.
     b. The third and final Stakeholder/Public Meeting was held December 8th

  • The 1st concrete curb was poured on April 12th, 2017 (rejected)
  • New Curb poured on April 27th & accepted by City Inspector

Staff continues to assist City of Moore IT with the ArcGIS Server and Portal for ArcGIS.

Onsite training continues as necessary for editors and data managers.