Little River Park Sewer Interceptor

Status: Active
Project Info
Work Order #: 
I-03-W-LMA
Category: 
Releasing Department: 
Capital Planning & Resiliency
Files
Events

No events have been scheduled for this project.

General Description: 

Sewer interceptor along the drainage channel located behind the Kings Manor housing addition.

Vendors

Cabbiness Engineering

The general scope of work for this project will include the development of sanitary sewer rehabilitation and/or replacement construction plans, from the project conception through construction completion. All design and construction requirements of the City of Moore and the Oklahoma Department of Environmental Quality, will be followed for the rehabilitation and/or the replacement of 9,000 linear feet of the 12”, 18” and 21” Little River Park Sanitary Sewer Interceptor. It is generally understood the scope of work will encompass, but not be strictly limited to: topographical survey; drainage basin and field reconnaissance; utility investigations; development of a preliminary engineering report that will include design concepts, identification of construction issues, preliminary construction costs and general recommendations for the work; preliminary field review meetings with staff and other stake holders; conduct utility conferences with all effected utility owners; completion of final construction plans; a final field review meeting with staff; preparation of bidding documents; bidding services and support; construction administration; and the culmination of the project by the delivery of as-built plans.

Maximum Contract Price: 
$99,130.00
Procurement Narrative: 

A City Request for Proposal announcement was made on May 13, 2015 for Civil Engineering Services for Disaster Recovery. Proposals were accepted until June 4, 2015 and 23 proposals were submitted. The following firms were selected:
1.Meshek & Associates
2.Poe & Associates
3.Cabbiness Engineering
4.CEC Infrastructure Solutions

Matthews Trenching

The work will consist of the construction of the Sanitary Sewer Interceptor Rehabilitation/Replacement at the Little River Park, Moore, Oklahoma.

Maximum Contract Price: 
$1,271,018.75
Procurement Narrative: 

A City Bid announcement was made on January 18, 2017 for Little River Park Sanitary Sewer Interceptor Rehabilitation/Replacement. Bids were accepted February 20, 2017 and four submittals were received. Matthews Trenching was awarded the contract on April 3, 2017.

Project Updates

Engineering Update: Project construction began approximately May 1, 2017. Television inspection has been completed for a portion of the line to be rehabilitated. Change Order No.

Engineering Update: Project construction began approximately May 1, 2017. Television inspection has been completed for a portion of the line to be rehabilitated.

Project construction began approximately May 1, 2017. Television inspection has been completed for a portion of the line to be rehabilitated.

Engineer Update: Project construction began approximately May 1, 2017. Television inspection has been completed for a portion of the line to be rehabilitated.

Engineer Update: Project construction began approximately May 1, 2017.

Project construction began April 24, 2017. Television inspection has been completed for a portion of the line to be rehabilitated.

  • Project has been advertised for bid and bids were opened on February 24, 2017. Project is scheduled to be awarded on April 3, 2017.