August 2017

Project construction began approximately May 1, 2017. Television inspection has been completed for a portion of the line to be rehabilitated. Change order has been completed to change approximately 300 to a bore to protect trees at the north end of the park, extend concrete apron on RCB under 4th Street, and realign at Janeway Circle. Construction is approximately 50% complete.

From 7-31-17 to 9-1-17 work was performed from MH 21 to MH 8.  For the month of August, 1,467 of of line has been installed along with 10 manholes.